NDCL: CTO-ICB-01-081-82

NDCL: CTO-ICB-01-081-82

Status: Completed

Project: Supply, Delivery, Installation, Testing and Commissioning of Datacenter Infrastructure and its Accessories

Location:
DC-1
Nepal Doorsanchar Company Limited (Nepal Telecom)
Jawalakhel, Lalitpur, Nepal

DC-2
Nepal Doorsanchar Company Limited (Nepal Telecom)
Padsari, Bhairahawa, Nepal

Job Description:
Control panel with auto mains failure: Three Power ATS Controller for dedicated ACB of rated capacity for output two generating set (750kVA) and input of city supply (750kVA).

Load ACB at the output of each control panel for 750kVA.

Sample units were carried out routine tests as per the relevant IEC standards and the routine test reports was made
available at the time of inspection to

NEEK representative: Mr. Bishesh Bhattrai,

Huawei representative: Mr. Firoj Khan

Routine test included:
1. Visual Inspection

2. Inspection of wiring and electrical operation

3. Verification of insulation

4. Verification of protective measures and continuity of protective circuits

5. Verification of insulation resistance

Contact Information